Nuclear plant owner Talen Energy Corp. says an initial 300 MW of data center development can proceed despite feds' rejection of grid link agreement to its Susquehanna facility in Pennsylvania's ...
Amazon.com (AMZN) told Bloomberg it’s committed to building a data center campus adjacent to a Pennsylvania nuclear plant after the ...
Members of FERC said the deal could raise power bills for the public and affect the grid's reliability. The Amazon-Talen deal ...
But FERC put the brakes on Amazon’s expansion plan, voting 2-1 against Talen’s (TLN) request, saying that the plan didn’t ...
Constellation stock was down about 10 percent on Monday. The FERC fight was brought by electric utilities Exelon and American Electric Power, which opposed the Talen-Amazon data center interconnection ...